Skip to main content

Golf Course Update


On Saturday and Sunday we dealt with snow, sleet, rain and high winds, but none the less our weekend staff managed to groom our bunkers very nicely (weed, smooth and rake). On Monday we applied a soluble fertilizer to our greens to help the bentgrass compete with the poa annua. We were also able to apply some slow release fertilizer to our tees to help the bluegrass and bentgrass compete with poa annua. Poa thrives in this wet, spring weather, so we try to help the other more desirable grasses along to the best of our ability.
We have had frost delays for the past two days, so during these delays we have taken advantage of the time and hauled fill down to the banks of the new cart path on #2 and we have also continued to back fill the pond.
Today we began to mow the intermediate rough around the fairways, this will take time to even out and obtain the density that we had last year.
Currently, the contractor is completing the ground work around the new eco-flo septic system that we installed at the Halfway House. Once they are done, we will be able to grade and seed the disturbed area.
As usual the Grounds Staff has been toiling with a few other areas on the golf course. We removed the mulch bed adjacent to #7 green and have added top soil and seeded the area with a shade mix. We installed a section of an old greens cover to help speed germination and growth of the seed (as you will see in the picture). We do still have some tree pruning to complete in the area of the seed bed, but it is on it's way. Later this week we will be doing some sod work on the stump holes and the remainder of the mulch beds that we removed from the playable areas of the golf course. The weather forecast for next week is not looking very good, so we will continue to take advantage of the great weather this week.

Comments

Popular posts from this blog

Bunker construction on # 17

The past few days we have been able to make great strides on the bunker project on #17. All three of the new bunkers have been shaped and drained. Tuesday morning Ian Andrew our consulting golf course architect, will be painting the final contours in the bunkers. We will then install the bunker boards and back fill with topsoil to the new edges. Once the edges are established we will add the new sand and await sod. The rain and snow that we recieved over the last couple of days has had little effect on the rough shaping process. We are hoping for some drier days to complete the fine tuning and sod prepping.

Golf Course Update

As our season slowly comes to a end our department has been working away at year end projects. We installed drainage in a few areas of the practice range and short game area. These areas were perpetually wet and caused turf and aesthetic issues. We have also been chipping away at the bunkers on #17, smoothing out the faces and recreating the grass edges. These bunkers suffered some severe frost heaving in the faces during the winter after they were built. Our team has removed a number of trees and brush from around our maintenance facility to allow some expansion of our operation. We are working away at clearing space to install aggregate bins and sufficient staff parking. This will also allow delivery trucks and semi's to access our facility without any issues. We are also removing the fallen trees and brush from the woodlot on the right side of #16 fairway. This is a challenging area to work as it is a peat bog and remains wet even in the hottest and driest of summers (like 2010)...

Finish Grading on #2 & #12 Tees

With the great weather that we have had the last two days, we were able to get the tees shaped and all of the tee mix out to the tees. In this picture here, Derek Vergeer (our contractor) is finish grading #2 Tee to be ready for sod. Unfortunately the forecast is for rain the next couple of days and could hold us up for a bit. We are doing out best to complete these projects in a timely manner, of course with this blog we will keep you updated.